2016 > 2017
-
Construction of the concrete floating foundation in Saint-Nazaire harbour by Bouygues Travaux Publics (80 workers on site)
-
Erection of the wind turbine onto the floater at quayside
-
Offshore pre-installation of the mooring system
2018 > 2020
-
Towing of the floater/wind turbine assembly to the offshore installation site of Centrale Nantes
-
Commissionning and connection to the grid
-
Demonstration period : monitoring, testing and validation of the outstanding performance of the entire floating system